Sample review

Renne Library Data Center UPS Replacements

This is the review we would have sent an electrical contractor who forwarded this invitation. It is a real public bid, read from the public documents only. Every line points to the page it came from.

OWNER: MONTANA STATE UNIVERSITY, BOZEMAN · ENGINEER: TD&H ENGINEERING · PPA NO. 24-1182
BIDS CLOSED 25 NOVEMBER 2025 · REVIEW PREPARED NOVEMBER 2026 AS A SAMPLE · NOT AFFILIATED WITH THE OWNER OR ENGINEER
SOURCES: PROJECT MANUAL · DRAWINGS E1 TO E6 · ADDENDUM 1 · BID RESULTS
INVITATION REVIEW · DIV 26 ELECTRICALData center UPS replacement, live university data centerBase bid + 1 alternate · bid due 25 Nov 2025, 2:00 PM
GO · 9 RFIs
Call
Bid, if you are registered in Montana and have a UPS vendor who can commit to a delivery date before the summer outage window. Otherwise pass.
Scope
Remove old UPS units, install a new 45 kW UPS, re-feed the panels, rewire the emergency power off. Second UPS is the alternate.
Addenda
1 issued, 18 Nov 2025. Adds EPO rewiring and halon control removal to the base bid. Outage notice becomes 2 weeks.
Risks
Outages only in academic breaks. Asbestos in the raised floor tile. No liquidated damages, but actual damages can be claimed.
RFIs
9 drafted below. The bid security one was live: both bids crossed $150,000 only with the alternate.

01Dates that matter

12 Nov 2025, 10:00Pre-bid walk-through, Plew Building. "Attendance is strongly recommended." Invitation to Bid
15 Nov 2025Last day for written questions and for substitution requests on Form 099: both at least 10 days before bid opening. ITB 5.1, 9.2
18 Nov 2025Addendum 1 issued. It must be acknowledged on the bid form. Addendum 1
25 Nov 2025, 14:00Sealed bids due, opened and read aloud at MSU University Facilities Management. Invitation to Bid
30 daysBids cannot be withdrawn after closing. ITB 8.2
15 daysTo sign the contract after award, with insurance, bonds and registration, or the bid security is forfeited. ITB 7.4, 7.6
19 Aug 2026Substantial completion. ITB 17.1

02Scope for the electrical trade

03What the bid must contain

04Risks to price

05RFIs, ready to send

  1. Where is the hazardous material remediation specified?Section 024119 says remediation "is specified elsewhere in the Contract Documents", but the manual has no remediation section. Please confirm whether any asbestos removal is in the base bid, and who performs it if the work disturbs the floor tile or wall texture.024119 1.7 D.1; Table of Contents
  2. Is the wall behind the new UPS locations textured with asbestos-containing surfacing?Sheet E2 note 3 asks us to remove surface-mounted boxes and devices on that wall. The IH report finds asbestos in the sand swirl texture on concrete walls, and the asbestos notes forbid drilling textured walls. Please confirm the wall type and the procedure for removing those boxes.E2 note 3 and asbestos note 2; IH report
  3. How many existing UPS units are removed in the base bid?Sheet E1 describes demolition of five existing UPS units; Section 011000 describes replacement of two. Please list the units removed in the base bid and in Alternate 1, and confirm battery disposal is ours for each.E1 scope of work; 011000 B.1; Addendum 1, item 4j
  4. Is the $150,000 bid security threshold measured on the base bid or on base plus Alternate 1?The Invitation to Bid says bids "equal to or greater than $150,000" need 10% of the total bid; ITB 7.2 says proposals "over $150,000". A base bid under the threshold with an alternate that takes it over is unclear.Invitation to Bid; ITB 7.2
  5. Which APC features are accepted in place of Eaton-specific ones?Section 263353 names the Energy Saver System, Line-and-Match battery cabinets and PredictPulse monitoring, which are Eaton product names. Addendum 1 lists APC vendors but records no prior approvals. Please confirm an APC unit meeting the ratings is compliant without these named features.263353 1.2, 3.3 C; Addendum 1, items 3a and 5
  6. Does start-up by an authorized partner meet the field service rule?263353 1.5 D requires field engineers employed directly by the manufacturer and rejects third-party service. Addendum 1 lists Nationwide Power for Eaton and CFT for APC. Please confirm their start-up and warranty service are acceptable.263353 1.5 D; Addendum 1, item 3a
  7. Are the service office map and maintenance contract offers due with the bid?263353 1.5 D and G say both are submitted or offered "with the proposal", but the bid form has no place for them. Please confirm whether they are due on bid day or with submittals.263353 1.5 D, G; Bid Proposal
  8. Which outage notice governs, and what are the 2026 windows?Supplemental Conditions 10.3.7 and Section 011000 ask for 72 hours or 3 working days; the drawings and Addendum 1 ask for 2 weeks. Please confirm 2 weeks governs and give the 2026 spring break and summer session dates.SC 10.3.7; 011000 F.2; E2 note A; Addendum 1, item 4c-i
  9. Is there a freight route to the base level?The north doors are recommended for heavy equipment, but they also have stairs. Please confirm whether an elevator or ramp is available, and whether MSU expects the contractor to provide stair rigging for the UPS modules and battery cabinets.Addendum 1, item 4e

06What happened

Two contractors bid. Both acknowledged the addendum and included bid security. Both base bids were under $150,000, and both totals crossed it only with the alternate, which is why RFI 04 mattered.

2

bids received. 3 contractors signed in at the walk-through

$99,795

low base bid. The other base bid was $121,461, 22% higher

$84,332

low price for Alternate 1. The other was $107,926, 28% higher

Source: MSU bid results and the Addendum 1 sign-in sheet. Contractor names are public there; we leave them out here.