Electrical scope of work template for bids
A bid scope sheet says, in plain lines, what your number includes and what it does not. General contractors level bids against it, and it is what you point to when a gap shows up after award.
01How to build it
Work from the specification table of contents and the drawing index, not from memory. Every Division 26 section and every sheet gets a line: included, excluded, or by others. Then add what lives outside the sections: demolition, temporary power, testing, outages, coordination.
02The template
ELECTRICAL BID SCOPE SHEET
Project: [name, owner's number]
Bid date: [date and time]
Bidder: [company, contact]
1. DOCUMENTS REVIEWED
Drawings: [sheet numbers and dates]
Specs: [sections, e.g. 260000, 260519, 260529, 260533, 260553, 263353]
Addenda: [numbers and dates]
2. INCLUDED, BY SECTION
[section] [what is included, in one line]
3. DEMOLITION AND DISPOSAL
[what is removed, who disposes of it, batteries and hazardous items]
4. TEMPORARY POWER AND CUTOVERS
[temporary feeds, bypass operations, number of outages, notice period]
5. TESTING, START-UP AND TRAINING
[field tests, manufacturer start-up, commissioning support, training]
6. COORDINATION
[EPO, BMS or monitoring, fire alarm, mechanical interlocks, owner IT]
7. EXCLUDED
[permits if owner-paid, painting, patching, hazardous material abatement,
after-hours premium unless stated, items marked by others]
8. CLARIFICATIONS AND ASSUMPTIONS
[answers to RFIs, assumptions priced where no answer came]
9. SCHEDULE ASSUMPTIONS
[outage windows, working hours, equipment lead time, completion date]
10. ALTERNATES
[each alternate, what it adds, priced separately]03A filled example
Parts of the sheet for a closed public bid: replacement of UPS units in a university data center. Every line comes from the bid documents.
| Line | What the documents say |
|---|---|
| Included, 263353 | New UPS-A, 45 kW / 45 kVA, 15 minutes at full load, 120/208 V 3-phase 4-wire, external maintenance bypass. 263353 1.2 |
| Included, feeders | #4/0 with #4 ground in 2-1/2" conduit; flexible metallic conduit under the raised floor, EMT above the ceiling for the UPS-A feeder. E2 note B; E5 |
| Temporary power | Temporary feed to the old UPS during changeover, removed once panels are on the new unit. E4, E5 |
| Coordination | New UPS units and existing HVAC wired to the existing EPO; EPO tests only under the engineer and owner IT. Addendum 1, item 2a |
| Demolition | All removed UPS units disposed of by the contractor, none returned to the owner. Addendum 1, item 4j |
| Excluded | Plan review and permit fees: paid by the owner. Permit notice |
| Schedule | Outages with two weeks notice in academic breaks; two outages a couple of weeks apart if both units are replaced. Addendum 1, item 4c |
| Alternate 1 | New UPS-B, removal of UPS-S4 and the wall-mounted maintenance bypass. 012300 3.1; E6 |
Read the full review of this bid →
04What data center jobs most often leave out
- Labor for outages outside normal hours, when the owner allows cutovers only at night or in breaks.
- Temporary feeds and bypass steps between phases.
- EPO rewiring, testing and the removal of old fire suppression controls.
- Coordination time for manufacturer start-up, one visit per unit.
- Rigging through narrow doors and stairs.
- Dust protection in a running room and battery disposal.
05Questions
Is a scope sheet the same as the scope of work in the contract?
No. The contract scope is what the owner or general contractor writes. The bid scope sheet is your reading of it: what your number includes and excludes. It lets the general contractor compare bids line by line, and it protects you when a gap shows up later.
Should exclusions go on a public bid form?
Only if the form allows it. Many public bid forms reject conditional bids, so on those jobs the scope sheet stays an internal pricing tool and open questions go out as RFIs before the deadline.