Invitation to bid checklist: what to check before you price it

Most bids are lost or regretted because of something in the documents nobody read in time: a walk-through, a bond threshold, an outage window. This is the checklist we run on every invitation, for electrical and MEP subcontractors.

BIDBACKER · UPDATED 25 NOVEMBER 2026 · 8 MIN READ

01What an invitation to bid is

An invitation to bid (ITB) asks for a sealed price on a defined scope by a fixed date and time. The package usually holds the invitation itself, instructions to bidders, a bid form, general and supplemental conditions, Division 01 requirements, the trade specifications, drawings and any addenda. Public owners often award to the lowest responsible bidder, so what you leave out of the price is your loss, not theirs.

02The five-minute bid/no-bid screen

Before anyone opens the drawings, answer five questions. Two or more wrong answers usually mean a polite no-bid.

QuestionWhere to look
Is it our trade and our size?Invitation, summary of work, bid form. Is it one prime contract or trade packages? Does the base bid alone fit your bonding capacity?
Are we allowed to bid?Instructions to bidders: licensing or registration in the state, prequalification, bid security, insurance limits.
Can we make the dates?Walk-through date and whether it is mandatory, question deadline, bid date, completion date, outage or access windows.
What does it cost to say yes?Bid security and its threshold, performance and payment bonds, prevailing wage, retainage, payment terms.
What can hurt us later?Damages for delay, discrepancy clauses, hazardous materials, equipment lead times, work in occupied or live spaces.

03The full checklist, document by document

  1. Invitation to bid. Bid date, time and place, delivery method, walk-through, bid security rule, where addenda are posted.
  2. Instructions to bidders. Question deadline, substitution deadline and form, withdrawal period, how the low bid is decided with alternates, what makes a bid non-responsive.
  3. Bid form. Every blank, words and figures, alternates, unit prices, addenda acknowledgment, signature authority, whether conditions or qualifications are allowed.
  4. General and supplemental conditions. Damages for delay, claim notice periods, bonds and insurance, payment and retainage, who pays permits, utility shutdown notice.
  5. Division 01. Summary of work, phasing, working hours, owner occupancy, alternates schedule, temporary facilities, closeout and warranty.
  6. Your trade sections. Basis of design and approved manufacturers, "or equal" rules, submittals, testing, startup, training, warranty terms.
  7. Drawings. General notes first: they carry the rules that never reach the specs. Then demolition, phasing and riser diagrams, and every note that says "by others".
  8. Addenda. What changed, what it adds to the base bid, and whether it moved any date.
  9. Appendices. Hazardous material surveys, geotechnical reports, existing conditions. They often decide who pays for surprises.
  10. Conflicts. Every place two documents disagree becomes either a question before the deadline or a risk you price.

04What data center electrical work adds

Live data centers change the risk more than the scope. On top of the list above, check:

05A real example

We ran this checklist on a closed public bid: a UPS replacement in a university data center. It found nine questions worth sending before the deadline. Three examples:

Bid security threshold written two waysThe invitation asked for security on bids "equal to or greater than $150,000"; the instructions said "over $150,000". Both base bids came in under that line and both totals went over it only with the alternate.
A remediation section that did not existThe demolition section said hazardous material remediation was "specified elsewhere". The manual had no such section, and the survey found asbestos in the raised floor tile.
Outage notice: 72 hours or two weeksThe supplemental conditions asked for 72 hours. The drawings and the addendum asked for two weeks and limited outages to academic breaks.

Read the full sample review →

06Questions

What is the difference between an ITB, an RFP and an RFQ?

An invitation to bid asks for a price on a defined scope and is usually awarded to the lowest responsible bidder. A request for proposals asks for an approach as well as a price and is scored on several criteria. A request for quotation is usually a short, informal price request for smaller work or materials.

When should questions go in?

Before the deadline the instructions to bidders set. In the bid used as the example here, written questions had to reach the engineer at least ten calendar days before bid opening, and the only addendum came out a week before bids were due.

Do I have to acknowledge addenda?

Usually yes, on the bid form. In the example bid, the addendum warned that failure to acknowledge it may disqualify the bid, and bidders were bound by addenda whether or not they acknowledged them.