Pre-bid RFI template, with real examples
A pre-bid request for information is the cheapest insurance a subcontractor has. One clear question before the deadline can turn a guess into an addendum that every bidder prices the same way.
01When and where to send it
Send it in writing to the contact the instructions to bidders name, usually the architect or engineer, before the question deadline those instructions set. Answers that matter come back as an addendum to all plan holders, and only written addenda change the documents.
02The template
PRE-BID REQUEST FOR INFORMATION Project: [project name and owner's number] Bid package: [trade / division] RFI no.: [01] Date: [date] To: [architect or engineer named in the instructions to bidders] From: [company, contact, email, phone] Response needed by: [date, before the question deadline] Reference [Spec section and paragraph, sheet and note number, addendum item] What the documents say [Quote the exact words. If two documents disagree, quote both.] Question [One question, answerable with a yes, a no or a number.] Why it matters to the bid [What changes in scope, cost or schedule depending on the answer.] Proposed answer [The assumption we will price if the answer confirms it.]
03Six rules that get RFIs answered
- One question per RFI. Two questions in one letter get one answer.
- Cite the exact place. Section, paragraph, sheet, note. The engineer should not have to search.
- Quote, do not paraphrase. Quoting both sides of a conflict makes the problem obvious.
- Propose an answer. "Please confirm X" is answered faster than "please clarify".
- Send early. Late questions are often answered after the last addendum, or not at all.
- Plan for no answer. Some bid forms reject conditional bids, so an open question becomes a risk you price, not an exclusion you write.
04Four worked examples from a real bid
From our review of a closed public bid: replacement of UPS units in a university data center. All quotes are from the public bid documents.
See all nine RFIs in the full review →
05Questions
What if the RFI is not answered before bid day?
Check whether the bid form allows qualifications. Some public bid forms reject conditional bids outright, as the form in the example did, so the unanswered question becomes a risk you price rather than an exclusion you write.
Who should the pre-bid RFI go to?
To the person the instructions to bidders name, usually the architect or engineer, in writing. Oral answers are normally not binding; only written addenda change the documents.