Bid bond vs performance bond: what each one covers and when your bid needs it

A bid bond promises that if you win, you will sign the contract and provide the bonds the job requires. A performance bond promises that once you sign, the work gets finished. The first protects the owner during bidding, the second during construction, and on public work both often appear in the same invitation.

BIDBACKER · PUBLISHED 26 NOVEMBER 2026 · 5 MIN READ

01What each bond covers

There are usually three bonds in a public invitation to bid, and they arrive at different moments. The bid bond goes in with your price. The performance and payment bonds are due after award, before the contract is signed.

BondWhen it is due and what it protects
Bid bondSubmitted with the bid. If the low bidder refuses to sign the contract or cannot provide the required bonds, the owner can claim against it to cover the extra cost of going to the next bidder.
Performance bondProvided after award. If the contractor fails to complete the work, the surety steps in to finish it or pay for finishing it, up to the bond amount.
Payment bondProvided after award, usually together with the performance bond. It protects the subcontractors and suppliers who work on the job if the contractor does not pay them.

A certified check or another bid guarantee can sometimes stand in for a bid bond. What the owner accepts, and in what form, is written in the invitation and the instructions to bidders, so that is where the answer comes from on every job.

02The federal numbers

Federal construction follows the Federal Acquisition Regulation, and the numbers are specific.

The bid bond is sized against your bid. The performance and payment bonds are sized against the whole contract and grow with change orders. That is why bonding capacity matters more after award than on bid day.

03What happens when the bid bond is wrong

In federal sealed bidding, a bid that does not meet the bid guarantee requirement must be rejected (FAR 28.101-4). The same section lists the cases where the problem is waived, and they read like a list of mistakes contractors actually make:

Waivers exist, but they are the contracting officer's call and can be refused in writing. A missing or wrong bond amount on a state or local job has no federal safety net at all. Check the bond against the documents before the envelope goes out.

04A real threshold question from a public bid

State, county and university owners write their own bonding rules into the invitation. In the Montana State University bid we use as our sample review, a UPS replacement in a university data center, the invitation asked for 10 percent bid security on bids "equal to or greater than $150,000", while the instructions to bidders said proposals "over $150,000".

That difference mattered. According to the published bid results, both base bids came in under $150,000: the low base bid was $99,795. Both totals went over the line only once Alternate 1 was added, at $84,332 for the low bidder. Whether security was needed depended on whether the threshold applied to the base bid or to the base bid plus the alternate. That is exactly the kind of question to send before the deadline; our pre-bid RFI template shows how we worded it.

05If you bid as a subcontractor

On a bonded prime contract, the general contractor carries the bonds to the owner. The general contractor may still ask you for your own performance and payment bonds on your subcontract, and the subcontract bid documents say so when it does. Read that section before you price, because the bond cost and your available bonding capacity belong in the number.

For smaller firms that cannot get bonded on their own yet, the U.S. Small Business Administration guarantees bid, performance and payment bonds issued by participating sureties, on contracts up to $9 million for non-federal work and up to $14 million for federal work. SBA charges no fee for bid bond guarantees; performance and payment bond guarantees carry a fee of 0.6 percent of the contract price (SBA surety bonds).

06Six checks before you submit

  1. The amount and its base. A percent of what: the base bid, the base bid with alternates, or a fixed sum. If two documents say it differently, send an RFI.
  2. The accepted form. Bid bond, certified check, cashier's check or letter of credit, and whether the owner's own bond form is required.
  3. The obligee. The owner named exactly as the invitation names it.
  4. Signatures and date. Signed by your company and by the surety, dated, with the project and solicitation number on it.
  5. The post-award deadline. How many days you have after notice of award to deliver performance and payment bonds, and in what amount.
  6. Your capacity. Whether your surety will back the whole contract, alternates included, not only the base bid.

These checks sit inside our broader invitation to bid checklist, under "What does it cost to say yes?".

07Questions

Is a bid bond the same as a performance bond?

No. A bid bond is submitted with the bid and protects the owner if the winning bidder will not sign the contract or provide the required bonds. A performance bond is provided after award and protects the owner if the contractor does not finish the work.

How much is a bid bond on a federal construction job?

Under FAR 28.101-2 the bid guarantee must be at least 20 percent of the bid price and not more than 3 million dollars. State, county and university owners set their own amounts in the invitation to bid.

When are performance and payment bonds required on federal work?

Under FAR 28.102-1, on construction contracts over 150,000 dollars. For contracts over 35,000 and up to 150,000 dollars, the contracting officer uses two or more alternative payment protections instead.

What happens if my bid bond is wrong?

In federal sealed bidding a bid that does not meet the bid guarantee requirement must be rejected, except in the cases FAR 28.101-4 lists, such as an unsigned bond submitted with a signed bid or a wrong date. On state and local jobs the invitation sets the rule.

Do subcontractors need performance bonds?

Sometimes. The prime contractor carries the bonds to the owner, but it may require its subcontractors to bond their own subcontracts. The subcontract bid documents say when that applies.